JKLR-Part(IV) OWP 26/1999 Back To Index |
(2001) 1 J & K LAW REPORTER
464 NARESH
KUMAR GUPTA
Petitioner OWP
No. 26 / 1999, decided on 14.8.2000.
Constitution of India Art. 226 - Petitioner bound by the terms of contract to refer
dispute, if any, to the arbitrator - Approached High Court to invoke extra-ordinary powers
of the Court under Art. 226 of the Constitution of India - Held : writ petition not
maintainable.
In essence,
the rights and obligations of the parties are sought to be worked out in the light of the
terms of the agreement, thus the controversy centres around the interpretation of the
terms and conditions of the contract which are binding on the parties and as a matter of
fact by medium of their pleadings they have reiterated such binding. In this back drop the
petitioner is not entitled to invoke the jurisdiction of this Court under Art. 226 of the
Constitution, for, such course will tantamount to saying good bye to the terms of the
agreement which cannot be permitted in view of the candid admission of the parties,
evidencing the fact that there relationship is governed by the agreement.
[Para 3] Advocates who appeared in this case : Cases referred : Chronological JUDGMENT AND ORDER
The petitioner-contractor entered into a works contract with the
respondents for construction
of buildings to provide accommodation for married GCOs/HAVs / OR at
Baramulla vide works contract No. CESZ-14 / 91-92, besides, accommodation for MED Regt.
at Pattan vide Contract SESZ / 07 / 93-94. He claims to have completed these works on 06/05/1997 and 06/01/1998 respectively. To substantiate the
contention, reliance is placed on the certificate issued by respondent No. 3 vide No. 8101
/ CESZ - 14 / 91-92 / 992 / EB dated
06/05/1997 which is said to have been issued in terms of
condition 49 of the General conditions of the contract enshrined in IAFW-2249. Relying on the certificate it is contended that
the respondents are bound to make the payment to the petitioner within the period
specified under condition 66. 2. The respondents
have vehemently opposed the
maintainability of the writ petition on the ground that no fundamental or statutory right of the petitioner has
been infringed. They have
contended further that the petitioner has failed to complete the work within the
stipulated period and has neither rectified the defects nor has he returned the unused
store items and breach of contractual obligations is ascribed to the petitioner in so many words. In this
background it is canvassed that the petitioner should have sought the settlement of the
dispute through arbitration under clause 70 of the IAFW-2249 which is extracted and
reproduced for facility of reference : 70-Arbitration: All disputes between
the parties to the
contract (other than for which the decision
of CWE or any other person is by the contract expressed to be final and binding) shall after the written
notice by either party to the other of them
be referred to sole arbitration of an Engineer officer to be appointed by the Authority mentioned in the tender document. 3. The
language of clause makes it very clear that in the event of dispute arising out of
contract, it is referable to the arbitrator. Whether a dispute has arisen out of the
contract, the pleadings of the parties assume significance and a cursory glance on the
same unfolds that the petitioner claims relief on the basis of recitals of the agreement whereas the respondents deny his
entitlement on the strength of the very terms and conditions of the agreement pressed into
a service by the petitioner. It is appropriate to notice that the case on hand does not
represent a situation where petitioner relies on one set of conditions and the respondents
on a different one but fact of the matter is that both the parties rely upon a set of
conditions contained in IAFW - 2249. In essence, the rights and obligations of the parties
are sought to be worked out in the light of the terms of the agreement, thus the
controversy centres around the
interpretation of the terms and conditions of the contract which are binding on the
parties and as a matter of fact by medium of their pleadings they have reiterated such binding. In this backdrop the petitioner is
not entitled to invoke the jurisdiction of this court under article 226 of the
Constitution, for, such course will tantamount to saying good bye to the terms of the
agreement which cannot be permitted in view of the candid admission of the parties,
evidencing the fact that their relationship is governed by the agreement. 4. Here it
is advantageous to refer to the judicial pronouncement of the Apex Court in State of U.P. v.
Bridge & Roof Co. (India) Ltd. reported
in AIR 1996 SC 3515 at 3520. In para (21), it was observed :
21. There
is yet
another substantial reason for not entertaining the writ petition.
The contract in question contain a clause providing
inter-alia
for settlement of disputes by reference to arbitration ( Clause 67 of the Contract). The Arbitrators can decide both
questions of fact as well as question of law. When the contract itself provides for a mode of settlement of disputes arising from the
contract, there is no reason why the parties should not follow and adopt that remedy and
invoke the extraordinary jurisdiction of the
High Court under Article 226. The
existence of an effective alternative remedy - in this case, provided in the contract
itself - is a good ground for
the court to decline to exercise its extraordinary jurisdiction under Article 226. The
said Article wasnt meant to supplant
the existing remedies at law but only to supplement them in certain well recognised
situations. As pointed out above, the prayer for issuance of a writ of mandamus was wholly
misconceived in this case since the respondent was not seeking to enforce any statutory
right of theirs nor was it seeking to enforce any statutory obligation cast upon the appellants. Indeed, the very resort to
Article 226 - whether for issuance of mandamus or any other writ, order or direction was
misconceived for the reasons mentioned supra. 5. In yet
another case, recent in point of time, the apex court in Asgar S. Patel v.Union of India reported in AIR
Supreme Court Weekly ( 25 / 2000 ) held : When
the parties enter into a clear, unambiguous and express contract creating mutual rights and obligations, the
parties are bound by it and the extraordinary jurisdiction of the High Court under Article
226 of the Constitution which is of discretionary nature cannot be allowed to be utilized for enforcing an obligation in
departure from the terms of the agreement. 6. Examining
the matter in the light of judgments of the
Apex Court (supra), the writ petition is not maintainable, accordingly, it is dismissed.
No order as to costs. ......... |